Expansion Plans

A new terminal is coming to Flamingo Airport!

In 2008, the airport began realizing their 15-year master plan.  This was plan was adopted by the island government in 2009, and Phase 1 (complete runway renovation) already has been completed in 2011.

Phase 2a calls for a new Air Traffic Control Tower, while Phase 2B will bring a new apron and two taxiways to the runway.  Phase 3 will realize a  new, state-of-the-art passenger terminal.  Phases 2b and 3 should be conducted simultaneously.  Currently, additional scenarios are also being reviewed.

 

Work on the new Rescue & Fire Fighting Station began on October 9th, 2014.

 